House Tour: West 22nd Street - Week 6

House Tour: West 22nd Street - Week 6

4869fde91c29cc6f3cf9d7f4f31c7a27ab180469
Maxwell Ryan
Jul 14, 2004

The clock ticks.... Alright, it don't look like much, but this pic at right shows one of the last blocks of triple layered insulation being mounted between the beams on the ceiling. The rest is all done. After pulling down the old ceiling, revealing the beams, removing all nails, planing and finishing the beams, installing electrical wiring, and now mounting custom sizes of insulation board all the wall along the ceiling, a big part of this job is done. MGR

See

Next Week:

Super pimpy doo stairs installed. Grid & stairs welded together (much fun, many sparks) Loft floor installed on top of steel grid Floors w/water based low tox TREX